California officials say repair costs at the nation’s tallest dam will be nearly double the original estimate of $275 million.
Department of Water Resources spokeswoman Erin Mellon said last week the contract with Kiewit Corp. at 770-foot Oroville Dam will grow to more than $500 million.
Kiewit project director Jeff Petersen said the project has required significantly more excavation and concrete than expected.
The main spillway and emergency spillway suffered significant damage during storms last February, prompting fears of massive flooding. Tens of thousands were evacuated but disaster was averted.
Petersen said the project is on schedule to finish pouring concrete on the main spillway by Nov. 1.
Related:
- Bad Design, Poor Construction Blamed for California Dam Damage
- Managers Made Errors in Handling California Dam Crisis
- California Awards Contractor $275M Contract to Fix Troubled Dam
- California’s Troubled Oroville Dam Gets Power Plant Restart
- Debris Pile Emerges from Water Near Troubled California Dam
- California Governor Calls for $437M in Spending for Flood Control
Topics California
Was this article valuable?
Here are more articles you may enjoy.